Time Schedule
-
20. 02. 2019
Selection of the arena location
-
10. 04. 2019
Commencement of coordination measures
-
18. 04. 2019
Study
-
30. 06. 2019
Commencement of project operations - Lipová tram loop
-
19. 09. 2019
Surveys
-
11. 11. 2019
Commencement of project operations - ARENA BRNO
-
13. 11. 2019
Commencement of project operations - areas and parking
-
15. 01. 2020
Commencement of project operations - Campus cable line
-
01. 02. 2020
Commencement of project operations - waste management, inward investment of Veletrhy Brno, a. s.
-
10. 02. 2020
Commencement of project operations - transportation frame
-
25. 02. 2020
Commencement of work to acquire demolition notice
-
26. 02. 2020
Commencement of project operations - reconstruction of Brno IV, BVV gate
-
15. 05. 2020
Commencement of project operations - Bauerova stage 0
-
2020-2021
Acquiring zoning and construction decisions
-
14. 01. 2021
Application for a joint permit (zoning decision and building permit) - technical infrastructure (water works): special building authority for water works OVLHZ MMB
-
14. 01. 2021
Application for a joint permit (zoning decision and building permit) - areas and roads I. Stage: special building authority for roads OD MMB
-
22. 01. 2021
The Regional Office of the Department of the Environment of the South Moravian Region concluded that the MULTIFINCTIONAL SPORTS AND CULTURAL PAVILION project is not subject to an environmental impact assessment of the project
-
29. 01. 2021
Application for a joint permit (zoning decision and building permit) - multifunctional hall: general building authority Brno střed
-
04. 02. 2021
Tender: concession - hall operator
-
2021
Obtaining a joint permit (zoning decision and building permit) - technical infrastructure (water works): special building authority for water works OVLHZ MMB, date: March - May
-
2021
Obtaining a joint permit (zoning decision and building permit) - multifunctional hall: obecný stavební úřad Brno střed, date: March - June
-
2021
Obtaining a joint permit (zoning decision and building permit) - areas and roads I. Stage: special building authority for roads OD MMB, date: March - June
-
2021
Work associated with felling carried out by the companies Brněnské komunikace and Veřejná zeleň města Brna, date: March – May
-
2021
Demolition associated with construction, date: May 2021 - January 2022
-
2021
Smyčka Lipová (DPMB a.s.) - issue of building permit, date: May - June
-
01. 12. 2021
Rada města Brna schválila zahájení zadávacího řízení na zhotovitele stavby
-
2021-2024
Realization of individual projects
-
2022
Výběr zhotovitele multifunkční haly
-
2022
Výběr správce multifunkční haly
-
17.2.2022
Multifunkční hala II. etapa - získání společného povolení souboru staveb
-
07. 12. 2022
Výběr provozovatele - společnost ARENA BRNO
-
21. 6. 2023
Schválení úvěrové dokumentace na zastupitelstvu města Brna
-
18.09.2023
Start the construction of the hall itself